The US Government is giving production of Columbia SSBNs priority over AUKUS Virginia commitments.
Rather than producing 2.33 Virginias per year to meet AUKUS commitments, the US Government is producing only 1.1 to 1.2 (page 56 reference below) Virginias per year.
This is in order to permit "top priority" (page 50) to be given to 1 Columbia class SSBN launch per year.
"One COLUMBIA Class SSBN represents approximately 2.5 [Virginia class] VACL SSNs in terms of build resources (manning) and tonnage." (page 62)
The reference is the US Congressional Research Service's Navy Virginia-Class Submarine Program and AUKUS Submarine (Pillar 1) Project: Background and Issues for Congress of February 11, 2025 at https://sgp.fas.org/crs/weapons/RL32418.pdf