March 4, 2016

Collins Midlife Upgrade/Extension - Companies, Tomahawks and Possible Timings

The most comprehensive, up-to-date Asia-Pacific sub numbers-types map I've seen - at March 3, 2016. Australia's six Collins subs may need to be upgraded with Tomahawk cruise missiles to keep pace with Klubs fitted to Kilo subs of India, Vietnam, China, Russia and perhaps two future Indonesian Kilos. (Graphic courtesy news(dot)com(dot)au with this clearer, larger, image)
--- 

The leaking of Top Secret Cabinet documents on Future Submarine project timings has prompted Submarine Matters to draw together many details on the Collins "life extension" (or "midlife upgrade"). The midlife upgrade may result in much work for Lockheed Martin in cooperation with Saab and Thales.

The Australian Defence Department apparently has been advising for years that the future subs would not be delivered until the early 2030s. 

Defence sources said the handover of a future submarine by 2026 was always more of a political aspiration (of former Prime Minister Abbott) rather than a sensible shipbuilding schedule.

Australia’s six Collins subs were launched between 1993 and 2001 which, after the standard 30 years of operation, would usually lead to decommissioning between 2023 and 2031. A submarine midlife upgrade would aim to keep them operating until the mid-2030s.

In the meantime a midlife upgrade of the Collins might include more modern sonar, the latest software and hardware for its AN/BYG-1 combat system, derusting, new batteries, overhaul of the diesel engines and maybe introducing Tomahawks. The upgrade would cost much more than A$2 Billion total.

TOMAHAWK CRUISE MISSILES

An additional item which Australia might include in the Collins is Tomahawk (land attack and long range anti-ship) cruise missiles (compatible with the combat system) which would be launched through the torpedo tubes. Wikipedia records: "During the [Collins] construction phase, consideration was given to acquiring submarine-launchable Tomahawk cruise missiles; giving the [Collins submarines] the capability to attack land targets after minor modifications.[44] Plans to acquire Tomahawk or similar land-attack missiles remained under consideration until 2009, when the Defending Australia in the Asia Pacific Century: Force 2030 white paper was released; stating that land-attack missiles will instead be incorporated into the armament of the Collins-class replacement."

With the future submarine delay a decision not to include Tomahawks could mean Australia falling behind in a region with increasing numbers of submarine fired Klub land attack cruise missiles. This is noting that Kilo diesel electric submarines belonging to Russia, India, China, and Vietnam are being fitted with land attack Klubs missiles (with ranges varying from 300km to 2,500km (depending on user modifications)). Indonesia may also buy two Kilo submarines fitted with Klubs.

UPGRADE WORK FOR LOCKHEED MARTIN, SAAB AND THALES

The life extension may result in much work for Lockheed Martin in cooperation with Saab and Thales. This is noting that the AN/BYG-1 combat system to be upgraded in the Collins is intertwined with the broader sensor, communications and weapon systems of the Collins. Lockheed Martin, Saab and Thales are already working together on submarines solutions. This may allow them to provide an integration solution for most of the upgrades required by the Collins. See Lockheed Martin on Tomahawks for US and UK submarines.

----------------

Saab (as early as October 2015) publically anticipated the likely timeline of the Future Submarines and need for a midlife upgrade of the Collins. Nigel Pittaway in DefenseNews, October 10, 2015 reported:

“Saab Pitches Collins Submarine Upgrade

…Speaking at the Pacific 2015 Maritime Exhibition in Sydney last week, a Saab senior executive said …a Collins midlife upgrade [will be] a cost-effective measure to maintain capability…“In Australia, you have decided on a new submarine program, which is fantastic, but it’s not going to be here for a number of years…”

…Australia is looking to acquire up to 12 new conventional submarines under Project Sea 1000, but has a tight timeline if it wishes to avoid further full cycle docking overhauls, which will need to be performed on at least two submarines if the Collins needs extending beyond 2030.

…However, the slow progress of the program is causing concern that the submarines cannot be designed, selected and built in time to avoid a Collins life extension.

…[Gunilla Fransson, Saab’s senior vice president, Security & Defence Solutions] said that if Saab’s proposal for a Collins midlife upgrade is accepted, the work would be undertaken in Australia. “You sustain the Collins boats here in Australia and I don’t see any reason why you could not upgrade them here,” she said.

“Saab would certainly like to position ourselves to support Australia in an extended Collins life of type. You have a very capable local submarine company in ASC, which certainly has the capability to perform the work, together with Saab Kockums and other local Australian companies.”” [WHOLE DEFENSENEWS ARTICLE]

COLLINS TABLE

(heavily modified from Wikipedia)

Name
Laid down
Launched
Commissioned
Usual Decommissioning 30 years after Launch. (Upgrade to operate to?)
Namesake
14 Feb 1990
28 Aug 1993
27 Jul 1996
2023
(2033?)
Vice Adm  Collins
1 Mar 1991
15 Dec 1995
31 Jan 1998
2025
(2034?)
Rear Adm  Farncomb
19 Mar 1992
14 Mar 1997
10 Jul 1999
2027
(2035?)
Capt Waller
4 Mar 1993
12 Mar 1998
23 Feb 2001
2028
(2035?)
17 Feb 1994
1 May 1999
23 Feb 2001
2029
(2036?)
Seaman Sheean
12 May 1995
26 Nov 2001
29 Mar 2003
2031
(2036?)
Lt Cdr Rankin

Pete

Australian "Delay" in Receiving the Future Subs

Note that the new submarines will only begin to be built in about 12 years time - for entry into service not in the late 2020s but the early 2030s. 

There is currently a political confrontation between former Prime Minister Abbott and current Prime Minister Turnbull over what Abbott perceives as a new submarine "delay". 

Only beginning the build in 2027 may cause much uncertainty for the winning contender. The delay may effect TKMS and DCNS less as there is a full export or foreign build order book for TKMS (for Greece, Turkey, Egypt, Singapore, Israel and South Korea) and almost full for DCNS (India and Brazil).

For Japan it is a long wait. The delay may benefit Australia with the opportunity for Lithium-ion Batteries (LIBs), new diesels and the new snorkel system being operationally tested in Japanese Soryu Mark 2s and new, post Soryu class, over a longer period. If Japan is chosen see the Australian build details in red in the SORYU TABLE below. 

If TKMS or DCNS are chosen Australia may benefit from those companies spending a longer period developing and testing new air independent propulsion (AIP) technologies and also LIBs.

Without the CEP contender even being announced the "delay" controversy should serve as a warning to contenders about how political the new submarine issue is in Australia. Australian government decisions may continue to be surprising, personality and election driven. Different Prime Ministers and Coalition versus Labor governments may have conflicting ideas as to when and where the submarines should be assembled.

SORYU TABLE (with earlier Oyashios, as at March 22, 2016)
SS
No.
Build No
Name
Pennant
No.
MoF approved amount ¥ Billions & FY
LABs, LIBs, AIP
Laid Down
Laun
-ched
Commi-ssioned
Built
By
5SS
8105
Oyashio
SS-590/ TS3608
¥52.2B
FY1993
LABs only
 Jan 1994
Oct 1996
Mar 1998
 KHI
6SS-15SS
Oyashios
10 subs
8106
-8115
various
SS-591-600
¥52.2B per sub
FY1994-FY2003
LABs only
 Feb 1994
Mar 2008
 MHI
&
KHI
16SS Soryu
Mark 1
8116
Sōryū
SS-501
¥60B FY2004
LABs + AIP
Mar 2005
Dec 2007
Mar
2009
MHI
17SS
8117
Unryū
SS-502
¥58.7B FY2005
LABs + AIP
Mar 2006
Oct 2008
Mar
2010
KHI
18SS
8118
Hakuryū
SS-503
¥56.2 FY2006
LABs + AIP
Feb 2007
Oct 2009
Mar
2011
MHI
19SS
8119
Kenryū
SS-504
¥53B FY2007
LABs + AIP
Mar 2008
Nov 2010
Mar
2012
KHI
20SS
8120
Zuiryū
SS-505
¥51B FY2008
LABs + AIP
Mar 2009
Oct 2011
Mar
2013
MHI
No
21SS
No 21SS built
22SS
8121
Kokuryū
SS-506
¥52.8B FY2010
LABs + AIP
Jan 2011
Oct 2013
Mar
2015
KHI
23SS
8122
Jinryu
SS-507
¥54.6B FY2011
LABs + AIP
Feb 2012
Oct 2014
7 Mar 2016
MHI
24SS
8123
Sekiryū
SS-508
¥54.7B FY2012
LABs + AIP
Mar 2013
Nov 2015
Mar 2017
KHI
25SS
8124
SS-509
¥53.1B FY2013
LABs + AIP
Oct 2013
Nov 2016
Mar 2018
MHI
26SS
8125
SS-510
¥51.7B FY2014
LABs + AIP
?
?
Mar 2019
KHI
27SS
Soryu
Mark 2
8126
SS-511
¥64.3B FY2015
LIBs only
?
?
Mar 2020
MHI
28SS
8127
SS-512
¥63.6B FY2016
LIBs only
?
?
Mar 2021
KHI
29SS
?
?
 1st of New
Japanese  Class
LIBs only
?
?
2023?
MHI?
Aus1
?
?
1st of new Aus class (if Japan chosen)
LIBs only
2028?
2030?
2033?
in Aus or Jpn?
Aus2 to 12?
?
?
between 5 and 11 additional Aus subs
LIBs only
from 2029?
from 2031?
from 2034?
in Aus or Jpn?
Table courtesy of information provided to Submarine Matters. LABs = lead-acid batteries, 

AIP = air independent propulsion, LIBs = lithium-ion batteries.  



Pete