November 19, 2026

Malaysia's Submarine Availability: Second Article of Three

Malaysia manages its two Scorpène-class submarines on staggered maintenance schedules at the Teluk Sepanggar naval base in Sabah so that at least one boat remains operational while the other is in dry dock.

First Major Refit Cycle (2015–2020)
The first comprehensive refits were executed by Boustead DCNS Naval Corporation (BDNC), a joint venture between BHIC and Naval Group, with a contractual target of roughly 18 months per boat: [1, 2]
SubmarineCommissionedRefit StartReturn to ServiceKey Details
KD Tunku Abdul RahmanJan 2009Nov 2015May 2018First-of-class in-country refit; hull repairs and exhaust diffuser upgrades.
KD Tun Abdul RazakOct 2009Mid-2017Apr 2020Began sea trials in late 2019; completed full return during COVID-19 patrols.
Current & Upcoming Overhaul Cycle (2025–2030+)
  • Routine Sustainment (2025–2030): At LIMA 2025, the Ministry of Defence awarded a five-year, RM1.02 billion (~US$241 million) maintenance and repair contract to BHIC Submarine Engineering Services (BSES) to cover ongoing in-service support and scheduled maintenance at Teluk Sepanggar. [1]
  • Second Major Overhaul: A separate major overhaul contract is projected to take roughly 2.5 years per submarine in the Teluk Sepanggar dry dock. Following the November 2026 Letters of Intent signed with Naval Group, Thales, and Safran, this upcoming overhaul window is expected to integrate the submarines' Mid-Life Upgrade (MLU) packages sequentially through the late 2020s. [1]
Operational Impact of Staggered Timelines
  • Single-Boat Bottleneck: During any 18-to-30-month dry-dock period, Malaysia operates with a single active submarine.
  • Training Constraints: Historically, when one boat enters deep refit, at-sea training days for new submariners are curtailed to preserve operational readiness on the remaining active boat. [1]